On the Record: LEED Laboratory experts weigh-in on sustainable laboratory design practices and related costs.
 |
| NREL Science & Technology Facility, a LEED
Platinum lab. Copyright, Bill Timmerman. |
|
Spearheaded by MHTN Architects, ED+C magazine
participated in an original roundtable event on of the real costs of LEED
certification for labs (of varying size and scope). In this unique, in-depth
on-the-record discussion, industry experts explored and analyzed some of the
big issues and often overlooked or understated details. The team also discussed
the National Renewable Energy Laboratory (NREL) Research Facility in Golden, Colo. The NREL actual
costs were compared to the EarlyEco computer run using the NREL
parameters.
Roundtable Overview
The purpose of the LEED Laboratory Roundtable was to discuss sustainable
solutions for research laboratories and to identify the potential costs and
savings for those sustainable solutions. Mortensen Construction has just
competed the NREL Research Facility in Golden, Colo., which was approximately
an $18,800,000 facility with 72,200 gross square feet. MHTN Architects Inc. has
developed the E$pec and EarlyEco software programs to anticipate and forecast
potential LEED costs. Both Mortensen Construction and MHTN Architects, Inc.
have agreed to share their sustainable cost estimating knowledge with the
readership. LEED for Laboratories has not yet been issued by the USGBC. The
Cost Roundtable is anticipating that the LEED for Laboratory requirements will
soon be issued by the USGBC. Note that not all credits were investigated and
discussed.
The roundtable included moderators Bruce Haxton and Michelle Hucal, and
participants Dan Amon, Janet Baum, Glen Beckstead, Cara Carmichael, Gabriela
Klieman, Paul Mathew, Geoff McMahon and Sean Wennerstrom. Full biographies on
the experts can be found below. Here is a significant selection from the
two-day event’s transcript.
LEED Laboratory Cost Analysis Overview
Haxton - Mortenson Construction has just completed the National Renewable
Energy Laboratory (NREL), in Golden, Colorado. They supplied the team with
input forms for EarlyEco that consists of 40 items. The EarlyEco works by
itself or works in tandem with the E$pec estimating system and anticipates what
the LEED costs and savings on a credit-by-credit basis. The EarlyEco program
output identifies LEED credits, cost per square feet, relative first cost,
annual savings, simple payback in years, LEED-related professional design fees,
and total approximate cost. The last two column lines permit the owner to
identify what they feel is most sustainable for them. By dividing the total
approximate cost by the sustainable index you obtain the cost per sustainable
unit. This cost per sustainable unit permits the sustainable professional to
identify the most cost effective credits with the highest sustainability for
the site and client.
At the beginning of design, MHTN presents the full list of sustainable opportunities
for a project, showing the wide range of potential options. The client can then
describe their vision of the project and what their specific sustainable goals
and budgetary parameters are. Once their goals and budget are defined, the
design team can focus on how to accomplish those goals within the client’s
budget. When both E$pec and EarlyEco are used together, they can anticipate
both the traditional construction cost and the LEED credit costs. The EarlyEco
system also has the design synergies built into the computer program formulas
within the program. However since the software system is not automatic it still
requires experienced sustainable team members like Glen Beckstead, Bruce
Haxton, or Cara Carmichael and other very experienced sustainable consultants
and estimators to use the software in an intelligent fashion to include
potential synergies among sustainable design solutions.
MHTN has been asked numerous times if the EaryEco and E$pec software are for
sale. The computer systems need the experience of the MHTN staff to fully
utilize their capabilities; therefore the systems are not for sale. However
MHTN is sharing its knowledge with the readership in hope of furthering cost
effective sustainable designs.
LEED Laboratory Programming Phase
Baum – In the early part of the design process, we start with programming, and
when we are doing a project that we know will be LEED Certified or even just
complying with LEED guidelines, we look at the exhaust devices that might be
required in the laboratory and understand the operating or performance
characteristics of the ventilation system. For cost control, we start in
programming to model construction costs. Because the cost is intimately
connected with the square footage, we track any changes in the square
footage.
Entire Building Systems Design Approach
Carmichael – It seems like each credit has very individualized cost
implications when really, buildings should be thought of as many systems working
together. If we consider the idea of tunneling through the cost barrier where
there are capital cost additions as well as cost subtractions. I wonder if we
could create an alternate reference list on what other factors might weigh into
this. For instance, on a site where a green roof were incorporated which
reduced overall stormwater runoff and resulted in smaller drainage systems,
perhaps the calculator could indicate the synergies between
strategies?
LEED Laboratory Mechanical Systems
McMahon – I want to go back to something that Cara Carmichael said in the last
section relating to whole building solutions. That is the key to cost control.
Having cost estimating capability coupled with energy cost impact analysis —
plus additional first cost analysis — is critical to the process. By doing
that, you can enhance the team’s ability to make good decisions about which
measures to incorporate into the design process.
LEED Laboratory Credit
Cost Discussion
Haxton – The cost analysis team discussion consisted of four hours of
discussion regarding sustainable laboratory designs, costs, savings and LEED
credits. The narrative was significantly reduced into an article to describe to
the readership the impact of costs on each LEED credit. The LEED credit cost
discussion is listed below by LEED section, credit, and
prerequisite.
SUSTAINABLE SITES
SS Prerequisite 1: Construction Activity Pollution
Prevention
Beckstead – Many jurisdictions are making this a code requirement. Do not
consider it a cost for LEED if it is a code requirement. It is difficult to
price in a particular building without understanding where the facility is at,
and knowing the various conditions such as slope, but a good average is about
$.07 per square foot of site.
SS Credit 2: Development Density & Community
Connectivity
Beckstead – Development Density is a matter of doing the calculation and
determining if you meet the credit. This task may range from about $2000 to
$5000.
Credit SS 4.2 Alternative
Transportation: Bicycle Storage
& Changing Rooms
Beckstead – For Credit SS 4.2 most people think if they put in a bicycle rack
they will get a point and it will be very inexpensive. The showers and changing
rooms can be expensive. If you’re already building them, you can take advantage
of them very inexpensively. What I do is provide bike racks for 5 percent of
the occupancy of the building.
Credit SS 4.3 Alternative
Transportation: Low Emitting & Fuel Efficient Vehicles
Beckstead – For Option #1, provide vehicles for 3 percent of the building
population. Rather than buying them, I rented them. I could get a price that
was reasonable so I rented the vehicles. Option #2: Provide preferred parking
for low-emitting and high-mileage vehicles. I have a $150 sign up for 5 percent
of the total people to cover the preferred parking
requirement.
Credit SS 4.4 Alternative Transportation: Parking Capacity
Beckstead – For preferred parking capacity, the size of the parking is not to
exceed the zoning requirement. In this particular case, I am showing a $72,000
savings on your laboratory building because there is less parking. There is a
savings in putting in less asphalt parking area.
Credit SS 5.1a and b – Site Development: Protect and Restore
Habitat
Beckstead – In this case, there is a savings most likely because we are using
less paving. There are two or three different ways to figure this, in 5.1; a
and b, it is a matter of looking at what plant materials are being used, and
making sure it is native to the area. We are showing a savings of $24,000 on
this point.
SS Credit 5.2: Site Development:
Maximize Open Space
Beckstead – If more vegetation is needed to meet this requirement. I would
suggest reducing paved area and deducting $1-$2 per square foot of paving
reduction.
SS Credit 6.1: Storm Water Design: Quantity Control
Beckstead – There are many different ways to meet the requirements. In this
case we have used some swales. We did not use a vegetated roof, but that would
assist in quantity control as well. Total cost is $13,200.
SS Credit 6.2: Storm Water Design: Quality Control
Wennerstrom – If natural treatment can happen; the cost would be minimal
because it would be incorporated into the landscape. In Colorado, the natural
treatment would be the only way because stormwater has to be returned with in
24 hours per the local ordinance.
SS Credit 7.1: Heat Island Effect: Non-Roof
Wennerstrom – To use some other paving type could get into premiums in the $3-5
per square foot range. Shading may become more cost effective if the site
warrants a good parking lot layout for this approach to be used. The trees may
impact other credits because, in Colorado, you want to have temporary
irrigation for more than one year on trees especially.
SS Credit 7.2: Heat Island
Effect: Roof
Wennerstrom – If you use a vegetated roof and take cost into consideration the
structure and the additional waterproofing, this credit becomes expensive. On
some previous, project this has resulted in cost over $30 per square
foot.
Beckstead – That is why I used $15 and it goes up from there for a vegetated
roof. If the purpose of a vegetated roof satisfies other requirements, such as
reduction of energy use, this may justify the additional
costs.
SS Credit 8: Light Pollution Reduction
Beckstead – Light pollution reduction is more than cut-off fixtures on exterior
lights. It has to do with interior lights also, so there are operating costs
that can be saved by controlling when lights go off. Total costs will range in
the $.35 per square foot or $25,000 for this project.
SS Credit 9: Safety and Risk Management
Haxton – What would you suggest as a rule-of-thumb cost of commissioning for
equipment?
Baum – I don’t have a lot of data on that. On a recent lab building project
we’re setting aside 5 percent of the cost of the equipment for certification,
testing and calibration.
WATER EFFICIENCY
WE Credit 1.1 Water Efficient Landscaping: Reduce by 50
percent
Glen Beckstead – We are finding that water-efficient landscaping is one of the
easiest credits to obtain. That may be only because we’re in Utah and we can change the type of grass
seed to save 50 percent of the water. In most cases, we find this is very
effective in reducing the water use by much more than 50 percent. This is a
point that can save both construction costs and water. The irrigation system we
put in can be smaller and less complex. In this project we show a $10,000
construction cost savings.
WE Credit 1.2: Water Efficient
Landscaping: No Potable Water Use or No Irrigation
Wennerstrom – This credit is hard to achieve in Colorado because of the desert like climate.
We can have this type of landscaping. However, it is only green when there is a
lot of rain or in the spring, which is not always desirable by the owner/design
team. Non-potable water is at a premium and typically used in parks and golf
courses to make them green. If you are lucky enough to have non-potable water
close by, the use would be encouraged.
WE Credit 2: Innovative Wastewater Technologies:
Wennerstrom – I have not attempted to look at this credit as the water they
typically use is needed for dilution or their research. If the standard
plumbing bathrooms are a large enough portion of the building, I would think
this could be achieved with a small cost premium. It would all relate to the
ratio of lab fixtures to other fixtures.
WE Credit 3.1 and 3.2: Water Use Reduction: 20 percent to 30
percent
Wennerstrom – To address all of these water efficiency requirements, including
in the building, we’re almost always going with low-flow urinals. We’re almost
always getting an innovation point because we do more water reduction in our
buildings with no extra cost. It costs about $100 per fixture, which almost
runs through all of these water use credits. They are easy to look at and easy
to get without a great deal of cost.
ENERGY & ATMOSPHERE
EA Prerequisite 1: Fundamental Commissioning of the Building Energy
Systems
Beckstead – Fundamental commissioning is absolutely essential in a lab and is a
little more expensive than standard buildings. Commissioning is running about
$1.25 to $1.75 per square foot.
McMahon – We benchmark it a little differently, I usually think about it as 1
to 2 percent of the costs of the systems to be commissioned. Relative to
mechanical systems a reasonable assumption would be 1 ½ percent of the system
costs.
EA Prerequisite 2: Minimum
Energy Performance
Beckstead – Again it is one requirement that I very often do not include as a
cost for LEED because most jurisdictions require a minimum energy use
requirement. If costs need to be applied here they can be around $.80 per
square foot but the payback is very short, approximately 2¼
years.
EA Prerequisite 3: Fundamental Refrigerant Management
Wennerstrom – This credit is not as big of an issue these days compared to the
old refrigerant. Unless there is some process that needs the old refrigerant, I
would think this cost is minimal if any cost should be used at
all.
EA Credit 1: Optimize Energy
Performance
Wennerstrom – This cost would be hard to pinpoint at the early stages. We have
achieved efficiencies from upgrading the enclosure so we could downsize the
equipment and adding recovery systems so we can have “free cooling”. I would use
a cost of $1-3 per square foot for minimal enhancement for the first couple of
points. I would think it will go up substantially from there in a laboratory
project.
EA Credit 2: On-Site Renewable Energy
Beckstead – This one depends on how you get paid back for your power; what kind
of power you’re going to generate.
McMahon – I was looking at the numbers that you have on the renewables. They
look pretty aggressive to me. They’re all in a range of ten years and we have not
seen that. We would typically see 25 years or higher.
Mathew – Clarification — Geoff is this including subsidies or excluding
subsidies?
McMahon – Excluding subsidies. With Subsidies it can get better but on a
dollar-to-dollar basis 25 to 30 years has been our experience.
EA Credit 3: Enhanced Commissioning
McMahon – I think the $.50 per square foot you have used is a good incremental
cost of enhanced commissioning over standard commissioning.
EA Credit 5: Measurement
& Verification
McMahon – The measurement and verification cost is a hard one because
laboratory users and owners tend to be sophisticated users of control system so
often the incremental costs of getting that point is not great, say $.15 to
$.25 cents per square foot. On the other hand, when you get a user who is
coming in on a very low level in terms of the level of instrumentation they are
providing, that cost can get significantly higher.
EA Credit 6: Green Power
Wennerstrom – Typically we have found this to be an owner cost. It is not
difficult to calculate this number; find the expected electrical load and
purchase the amount of green power needed to get this point or (approximately
$10,500 for this project).
EA Credit 7 Right-sizing Laboratory Equipment Loads
Baum – In this case not only the culture of the institution but the culture of
the engineering group that we work with influences the savings. Sometimes we
are able to get good factual knowledge about the operation of equipment, but
often we only get projections of its importance on the people who use the
equipment.
McMahon – I think the savings can be pretty significant in terms of first cost,
especially when you’re talking about a biological lab that is load driven. If
design loads are reduced from approximately 8 watts per square foot to around
three, there is a significant decrease in capital cost associated with air
handlers, ductwork, associated piping, etc.
Baum – We work with the engineers on the diversity factor they feel is
reasonable for a particular application. Sometimes, for instance in regulatory
testing laboratories or forensic laboratories, we are not allowed much
diversity for plug loads. This is based on the 24/7 operation of those labs as
well as the critical nature of those instruments on evidence
analysis.
Beckstead – This point can save money in construction costs as well as
long-term energy costs. In this project we are using a construction savings of
about $4,000 and a yearly electrical savings of $18,000.
MATERIAL AND RESOURCES
MR Prerequisite 1: Storage & Collection of Recyclables
Beckstead – This point is usually achieved by giving people the opportunity to
recycle by simple signage and collection points. This will seldom cost more
than $5,000.
MR Credit 2: Construction
Waste Management:
Wennerstrom – Now to the cost on waste management, we were just under a $1 per
square foot. We diverted about 80 percent.
Beckstead – That seems correct. We used $.50 per square foot for 50 percent and
$1.00 per square foot for 75 percent. If the site is located in a small
jurisdiction, they may not have recycling. In larger jurisdictions, it may be
either required or cost less.
MR Credit 2.1 – 2.2 Construction Waste Management: Divert 50 percent to 75
percent from Disposal
Beckstead – We find that diverting 50 percent is easy. When you start diverting
75 percent it is more difficult and may start costing money. The 50 percent
diversion in most large towns will probably cost nothing.
Wennerstrom – As this becomes more mainstream, I feel the cost for this credit
will be very minimal. At this point we usually have cost in verifying and
keeping the recycle sorted properly. This could be a cost for one laborer for
one-third to one-half of the duration of the project to manage and achieve
these desired rates.
MR Credit 3.1 Material Reuse: 5 percent
Wennerstrom – Hard to do with new construction. If furniture is used, this may
be achieved but it would be part of the FFE, which is not typically carried in
the construction budget, if there are any premiums to be figured.
MR Credit 3.2 Material Reuse: 10 percent
Wennerstrom – This is very hard to achieve in a Laboratory
Project.
MR Credit 4.1 and 4.2 Recycled Content 10 percent and 20 percent (post-consumer
+ ½ pre-consumer)
Beckstead – We find that 10 percent is fairly easy while 20 percent is very
difficult to achieve. You have to really work at it and we are showing extra
cost of about $.23 per square foot.
MR Credit 5.1 and 5.2 Regional Materials 10 percent to 20 percent Extracted,
Processed & Manufactured Regionally
Beckstead – Regional Materials are the same way. It depends on where you are at
and what type of building you are doing; 10 percent is not too hard, 20 percent
is difficult. We have not done one yet where we can get this credit at
reasonable costs. We feel that it would be around $1.75 per square foot to
accomplish this credit because we are located in a portion of the country where
distances are great.
MR Credit 6.1 Rapidly Renewable Materials
Beckstead – Rapidly renewable materials is changing every day because we’re
moving away from some of the things that we have always thought of as rapidly
renewable. We are using trees that are aged to be four inches instead of log
size. Still the average cost is about $.75 per square foot.
MR Credit 7 Certified Wood
Kleiman – If we have a good case for certified wood, we try to convince the
client to go for it — this is very hard. If I call a supplier they may tell me
it is between 10 to 15 percent more to have the certified
wood.
INDOOR ENVIRONMENTAL QUALITY
EQ Prerequisite 1 Minimum IAQ
Performance
Beckstead – Minimum performance sometimes can be dropped out of the cost for
LEED, because it is already something that you do based on local code
requirements.
EQ Prerequisite 2 Environmental Tobacco Smoke (ETS) Control
Beckstead – Environmental Tobacco Smoke – Something you should already do, but
I do show a cost of about $900 to cover signage. If it is a state law, it is
not a LEED cost.
EQ Prerequisite 3 Laboratory Ventilation
Mathew – That prerequisite actually has to do with meeting the minimum
requirements in ANSI Z 9.5. As I recall, most laboratories would be meeting
that anyway. We have cited certain parts that are relevant — mostly things
related are room pressure control, which again you mostly do in laboratories.
EQ Credit 1: Outdoor Air
Delivery Monitoring
Wennerstrom – Because most laboratories we build need a large volume of outside
air, the monitoring is only a small part of this credit. Control contractors
typically will charge around $2,500 per monitoring station. You could figure
some parameters based on this cost for figuring a parameter in
EarlyEco.
EQ Credit 3.1: Construction
IAQ Management Plan: During
Construction
Wennerstrom – Very little cost in a laboratory building as the contractors need
to achieve certain standards which are close if not better than LEED
standards.
EQ Credit 3.2: Construction IAQ Management Plan: Before Occupancy
Beckstead – The cost is minimal but includes some additional cleaning and
changing merv 13 filters at the end of construction. We have allowed $7,200
dollars for this option.
Wennerstrom – The two-week flush is typically hard because they need the
buildings to start their research. The cost for the second option in this
credit would be born out of spending some energy and the cost for filters to do
the early flush before people arrive. This energy cost would be born by the
owner and they should be made aware of this expense.
EQ Credit 4.1: Low-Emitting Materials-Adhesives & Sealants
Beckstead – Low-emitting materials and sealants is getting to be a zero cost.
We don’t write any of our specifications without using these products. I leave
a little cost in there to take care of a few things that might come up since
you need a particular kind of sealant in a laboratory.
EQ Credit 4.2: Low-Emitting Materials: Paints and Coatings
Wennerstrom – There is a small cost here and it is becoming more commonplace.
This will become an issue if there are highly corrosive areas or BSL 3 areas
that cannot be coated with standard-type products.
EQ Credit 4.3: Low-Emitting
Materials: Carpet Systems
Wennerstrom – This credit is becoming more standard and should not be a cost
increase to the project.
EQ Credit 4.4: Low-Emitting Materials: Composite Wood & Agrifiber
Products
Beckstead – There is a cost in there, and it can be a big cost. We are showing
about $2.00 per square foot.
EQ Credit 5: Indoor Chemical and Pollutant Source Control
Wennerstrom – This should not be much of a cost because in the labs we have
completed this is already accounted for by codes or the owner’s
preferences.
EQ Credit 6.1 Controllability of
Systems - Lighting
Beckstead – Controllability of lighting systems is one of the big questions
that still need to be investigated further depending on the application. We
find this to be an added cost of about $.25 per square
foot.
EQ Credit 6.2 Controllability of Systems - Thermal
McMahon – The cost of this item can be very high. It can involve the addition
of a large number of control zones. I believe it will be higher than the amount
you have indicated.
Beckstead – If you take the controllability of systems and thermal comfort
design at $250,000 that is a significant $3.50 per square
foot.
McMahon – The savings are often overstated, but there are other reasons to do
this. The quality of the environment can be significantly enhanced if it is
done correctly.
EQ Credit 7.1 Thermal
Comfort: Design
Wennerstrom – This credit has some synergy with the energy savings credit. If
you take care of the enclosure in the energy savings credit, the additional air
terminals/control points could be substantial if everyone gets separate
control. We usually figure this to be in the neighborhood of $2,500 to $4,000
per control point depending on building layout and control
needs.
EQ Credit 7.2 Thermal Comfort Verification
Wennerstrom – This should be a fairly easy process the design team could incur
to achieve this point from a survey standpoint. I would put the cost on the
design team side. If design and construction meets the desired design no
corrective action is typically needed.
EQ Credit 8.1 and 8.2 Daylighting & Views: Daylighting for 75 percent and
90 percent of Spaces
Carmichael – I think this is a challenging credit not only in terms of meeting
the intent of the credit, which is to improve design conditions, but it is also
a really hard one to quantify the cost of it. I think the 2 percent is a
reasonable metric to work within, and we encourage it to be done with a bigger
picture intention in mind — not just the LEED credit. The other part is looking
at the larger impact those measures are having. By utilizing daylight in the
space, you are not only reducing the number of electric light fixtures that you
need, but you are also reducing the internal heat gain you are contributing to
the space and you might be able to downsize or eliminate certain
systems.
EQ Credit 9.1 Indoor Environmental Safety: Contaminant Device
Commissioning
Mathew – I have heard a number around $500 per hood for 110 Commissioning
(9.1).
EQ Credit 9.2 Indoor Environmental Safety: Protection and Notification
Systems
Beckstead – Protection and Notification Systems is again safety protection and
the way I have analyzed this is to make sure you have alarms to tell someone
something is going wrong. For the lab building we are looking at it would be
around $.25 per square foot.
INNOVATION & DESIGN
PROCESS
ID Credit 1 Innovation in Design: Facility Used as a Teaching
Tool
Kleiman – Something that we see commonly now in innovation of design,
especially for academic labs, is LEED as a Teaching Facility, as a teaching
tool. It is not just for the people who work and do research in the labs, also
for the public or when they have big events. That is something we try to
integrate into our projects.
Baum – We have used two approaches. We have used electronic information kiosks
and learning walls, which displays a lot of information. Another is providing
duplicate controls of devices that show the monitors of the building so that at
any one time a student can look over on the display doors to see how many CFM
is being used or BTUH or Watts or whatever.
ID Credit 2 Innovation in Design:
Carmichael – Beyond some of the standard ID
credits: green housekeeping, environmental education, exemplary performance,
there are a few interesting examples in the LEED for Labs system. Those include
mini- environments, displacement ventilation, optimized utility services,
flexibility and modularity, and design for catastrophic events.
Cost Summary
Beckstead – LEED for Laboratories is different than what you have done in past
because it is not under NC.
Haxton – As you can see on the spreadsheet (see attached spreadsheet) we have
the building cost at the top, and the square footage to remind us of the
building we are dealing with. We then have the summary for the different
categories and certification. We take two extra credits to be on the safe side,
and pursue those 28 credits at a cost of $708,782. But the savings per year was
up at $330,804 category, which gives us a payback of 2.14 years. I would like
to have your reactions to these numbers as to whether these are reasonable or
not and what are your experiences?
Baum – Our experience is that these initiatives had to come in generally within
a five-year payback.
Kleiman – For the project we have in Scottsdale, there had to be a payback in
five years.
Haxton – The Gold payback was shown at 3.65 years and the Platinum was at 5.29
years. Even the Platinum seems to be a very rational approach to pursue for
this laboratory we were talking about.
Carmichael – None of these seem way off in my
experience. It is probably in the range and we have worked on many projects
that have been non-lab that have achieved the Platinum with no additional cost.
I know that the lab is different. I think in general I appreciate what is
trying to be done. I think it is a great start for providing this type of
information early in the design from people who really can apply this tool and
know how to integrate it into the larger context of design.
Wennerstrom – One of the main things I see benefit from EarlyEco is it creates
discussion early on in the process. We all recognize that the results are
conceptual, but at least you can identify the low hanging fruit and set a
realistic goal for the project. The design team and construction team can
monitor the goal through pre-construction, which is really what an owner
ultimately wants to know. With owner, design and construction team members
monitoring cost and design to achieve a common LEED strategy goal will
eliminate a common disconnect from different assumptions early on in the
process. When the assumptions do not align between all team members then
pre-construction activities don’t achieve the desired results from a
LEED/project standpoint. Setting expectations early using this tool with the
discussion points included in the EarlyEco are very important and I can see
contractors working in conjunction with the results to back up the ultimate
design.
Haxton – What we do is use this EarlyEco process that integrates the
contractor, consultants, and client in the decision making process. We try to
define their sustainability and budget goals. That is where it starts, then we
narrow it down to allow owners to see what the cost ramifications are for their
decisions.
Roundtable Summary
The discussion of the laboratory roundtable is to be a starting point for a
greater dialogue about sustainable laboratory design practices and the related
costs. The information in the discussion is for a special building on a special
site with an idealized square footage. It is meant for discussion purposes and
is not meant to promote one system over another; the information should not be
taken and applied to another building or site. Each site is very special and
the analysis and costs are specific to that particular site. When dealing with
laboratories, sustainable architecture, cost analysis, and specialized
engineering systems, seek professionals with experience in each and every
aspect of the building you are working with.
Further Study
MHTN has further studies that are planned to define the carbon footprint
information on each credit. This will help us analyze not only the least
expensive credits, the least expensive credits with the highest sustainability,
but also be able to factor in the credits that affect a minimized carbon
footprint with the lowest cost. Another area of special interest i