Web Exclusive: Green Within Budget
by Kent Muirhead AIA
May 7, 2007
Integrated
Cost Modeling Enables Project Team to Hit Gold Without Increasing Cost
The
flagship building of the new master plan for the University System of
Maryland’s Universities at Shady Grove campus has amassed enough LEED credits
to achieve Gold certification from the U.S. Green Building Council (USGBC). It
is the first building in the University System of Maryland to achieve Silver
certification or above.
The new 192,000 gross square-foot academic building is slated for completion in
June 2007 and has a trio of components — at three, four and five stories high —
united by a linear concourse. The program includes 40 learning spaces ranging
from 20 to 300 seats, 100 faculty offices, a learning resource center, a
student dining facility that seats 300, a fitness center, student services, a
computer lab and support services, and provisions for future wet-lab research
space.
By implementing a rigorous design process, the project team has achieved
ninety-three percent of the proposed sustainable design and engineering
initiatives without exceeding the project’s $45 million construction budget.
A New Master Plan
In
Fall 2000, the University System of Maryland established the Universities at
Shady Grove (USG), a collaboration of eight University System of Maryland
degree-granting institutions bringing top upper-level and graduate degree
programs to a single campus in Montgomery County. USG subsequently formed
relationships with organizations such as the Montgomery County Chamber of
Commerce and the Technology Council of Maryland.
The program’s success yielded an increase in enrollment, putting pressure on
available land, infrastructure, parking area and program space on the Shady
Grove campus. The original 1994 master plan had been developed using a suburban
model, therefore buildings were relatively small in scale — of one or two
stories in height — and dispersed over the campus with surface
parking.
The owner commissioned Cannon Design to develop a new master plan for the
50-acre campus as a prelude to designing the new academic building. Based on an
urban model, the new master plan doubles the existing density of the campus
with larger, closely spaced buildings. It eliminates existing and future
surface parking in favor of structured parking — enhancing sustainability by
reducing total impermeable surface area and preserving forested land.
Keys to Sustainability
The
design team maximized the sustainability of the new building by identifying the
location and size of the site and positioning the building to ensure optimal
solar orientation for its location in the northern hemisphere: maximum frontage
facing south and north, and minimum frontage facing east and west. Facades are
designed to control the apertures (windows) in each of the four elevations:
vertical sunscreens on apertures facing east or west, and horizontal sunscreens
in those facing south. Moreover, it is the organization of the building — the
effective combination of solar orientation, floor-to-floor height and interior
depth — that directly influences two major LEED categories: energy efficiency
and daylighting.
The design team began with 15 organizational ideas for the building before
arriving at the plan that is both functionally efficient and energy efficient.
Although an organizational scheme based on a simple “box” might be the most
functionally efficient, the building needs sufficient surface area to achieve
the daylighting goal albeit in an energy-efficient manner. Integrated cost
modeling enabled the team to reduce eight alternative organizational schemes to
three feasible alternatives, and then to one, at the programming phase.
What is Integrated Cost Modeling?
It
is important to understand the difference between energy modeling and cost
modeling. Energy modeling focuses on optimizing the building’s mechanical and
electrical systems to reduce lifecycle costs. Cost modeling is used to
calculate the total cost of construction.
When both cost and energy modeling are integrated or performed in parallel, the
design team is able to optimize both capital costs and energy savings.
Performed as part of the design process at each phase — programming,
schematics, design development, and at 50 percent completion of construction
documents — and at increasing levels of complexity and detail, cost and energy
modeling ensure that the project team makes the necessary course corrections in
design and/or engineering to attain the goals of the project without exceeding
the budget or schedule.
Not exceeding the budget or schedule is important on any project, but
particularly so for a public institution where capital costs and operational
costs are accounted for in two separate sections of the budget. Therefore,
arguments that are typically used to justify increased capital costs of a
sustainable building in terms of reduced lifecycle costs do not readily
apply.
Of the ten major energy savings initiatives proposed by the design team, 93
percent have been/are being implemented in the facility at no additional cost.
Through the use of sunscreens, improved glass, improved wall U value, improved
roof U value, reduced lighting (watts per square foot) level, added daylight
control in classrooms, VFD in chillers, and CO2 sensors, the design/engineering
team projects a total net-energy cost savings of 29 percent.
Lessons Learned
While
University System of Maryland’s original goal was LEED Silver certification,
the design team amassed enough credits to achieve Gold certification. Control
over site selection and orientation of the building are major factors in achieving
this higher level of LEED certification. As the owner and project team
progressed through the design process, they identified and initiated additional
opportunities.
Most institutional clients hire a construction manager (CM) for projects of this
scale, and USG was no exception. When an owner hires a CM, it is important to
do so as early in the project development phase as possible to take advantage
of the CM’s preconstruction services — in particular, cost modeling.
In addition, Cannon recommends that the owner hire an independent cost-modeling
consultant. While it may seem redundant to pay three consultants for
cost-modeling services, according to Cannon it is well worth the owner’s
investment. The reasons are when the three estimates and interpretations are
compared, the project team gains a better understanding of the scope of the
project, the cost of each component, and is better able to reconcile these
findings for the ultimate benefit of the owner.
The value of including LEED-accredited professionals on the project team also
cannot be overstated as these individuals provided a constant accounting of the
project’s credit status at every major project milestone.
While the use of integrated cost modeling is not a guarantee that a design team
will meet or exceed the owner’s LEED certification goals without increasing
capital costs, control over fundamental sustainable design issues — including
site selection and building orientation — also are keys. An owner can potentially
benefit greatly from this tool.
|